Oracle and Bloom Energy Expand Fuel Cell Deal to 2.8 GW
Oracle agreed Monday to purchase up to 2.8 gigawatts of power from Bloom Energy, the California fuel cell maker, to supply AI data centers across the United States. Fuel cells generate electricity from natural gas through a chemical reaction rather than combustion, producing power on-site without the grid connections and permitting timelines that can stretch for years. An initial 1.2 GW is already contracted and deploying now, with the rest following through next year. Bloom secured $7.65 billion in data center contracts across just 90 days in early 2026.
This deal is not really about power supply. It is evidence that the grid interconnection queue is so broken that building your own power plant on-site is now the faster path. Bloom delivered Oracle’s first fuel cell installation in 55 days, against a 90-day target. That is the benchmark grid utilities now have to compete with. The hyperscalers are quietly becoming their own utilities.
Watch whether Amazon and Microsoft accelerate their own off-grid strategies in response to Oracle’s lead. (Bloomberg)
ERCOT Projects Texas Grid Could Quadruple to 368 GW by 2032
Texas grid operator ERCOT told state lawmakers this week that peak electricity demand, currently at a record 85,508 megawatts, could nearly quadruple to 367,790 megawatts by 2032, driven almost entirely by data center construction requests. ERCOT, the independent system operator that manages the power grid for most of Texas, is responsible for matching electricity supply with demand in real time. CEO Pablo Vegas added a key caveat: these numbers represent every company that has filed to connect to the grid, not every company that will actually build. ERCOT is now replacing its old interconnection review process with a system called Batch Zero, which groups large new requests of 75 MW or more into batches for faster evaluation. The Federal Reserve Bank of Dallas estimates that wholesale power prices in Texas could rise as much as 50% from data center demand growth alone. (Insurance Journal)
EIA Projects US Power Demand Will Hit Records in Both 2026 and 2027
The U.S. Energy Information Administration projected this month that American electricity consumption will climb from a record 4,195 billion kilowatt-hours in 2025 to 4,260 billion kWh in 2026 and 4,388 billion kWh in 2027, driven primarily by AI data centers. If the forecast holds, it would mark the first time since 2007 that U.S. power demand has risen for four consecutive years, and the strongest four-year growth streak since 2000. The Department of Energy separately estimated that data centers accounted for 4.4% of all U.S. electricity use in 2023 and expects that share to reach 12% by 2028. For context: at 12%, data centers alone would consume roughly as much power as every home in the country combined. (EnergyNow)
Judge Orders GE Vernova to Stay in Vineyard Wind Contract
A Massachusetts judge granted Vineyard Wind a preliminary injunction this week, blocking GE Vernova from walking away from its turbine supply and maintenance contract. GE had sent a termination notice in February, citing more than $300 million in unpaid bills. Vineyard Wind is the first utility-scale offshore wind project in the United States and has faced construction setbacks, including a blade failure in 2024. The injunction keeps GE crews on-site through the legal proceedings and prevents a shutdown that would have stalled the project indefinitely. A separate court ruling earlier this month also cleared five major U.S. offshore wind projects to continue construction after the Trump administration missed a final appeal deadline. (Vineyard Gazette)
Eos Energy and TURBINE-X Target AI Data Centers with On-Site Storage
Eos Energy Enterprises and TURBINE-X Energy announced a joint development agreement Tuesday to deploy up to 2 gigawatt-hours of Eos zinc battery storage paired with on-site gas turbines at AI data centers, with first installations planned for 2027. Zinc batteries use more abundant and less expensive materials than lithium-ion cells and are designed for longer discharge cycles, making them suited to the sustained, high-draw loads that AI workloads generate. The pitch is speed: the partnership claims it can deliver hyperscale power capacity in months rather than the years required for traditional grid interconnections. Eos shares rose 12% on the announcement. (Globe Newswire)
Fermi CEO and CFO Exit as Project Matador Loses Momentum
Fermi Inc. lost both its co-founder CEO Toby Neugebauer and CFO Miles Everson in the span of two days this week, sending shares down 22%. Fermi is developing Project Matador, a planned gigawatt-scale AI data center campus in Texas that was positioned as one of the most ambitious buildouts in the country. The departures follow months of friction: a tenant pulled out in December, investors filed a class-action lawsuit, and executives faced pointed questions on the March 30 earnings call about the company’s inability to name a single signed anchor tenant publicly. Fermi announced a pivot to a “Fermi 2.0” strategy, creating an Office of the CEO led by two co-presidents and launching a search for a permanent chief executive. The company also disclosed it no longer expects to hit its original target of 1.1 gigawatts of capacity by end of 2026. (Axios)
Gas Turbine Shortage Is Slowing the AI Power Buildout
The rush to build natural gas power plants for AI data centers has run into a hard physical constraint: there are only three major gas turbine manufacturers in the world, none of which invested to scale during the previous decade of flat power demand. GE Vernova ended 2025 with an 80 GW backlog stretching into 2029. Siemens Energy is carrying a €136 billion order backlog, the largest in its history. Wood Mackenzie estimates turbine prices will rise 195% by end of 2026 compared to 2019 levels. Even if all three manufacturers deliver on their expansion plans, analysts estimate total output will rise only 20% to 25%, nowhere near enough to absorb the current wave of demand. The bottleneck is not just the grid. (Bloomberg)
DOE Directs FERC to Fast-Track Data Center Grid Connections
Energy Secretary Chris Wright directed the Federal Energy Regulatory Commission this month to initiate a fast-track rulemaking that would allow data centers and other large power users to file joint interconnection requests alongside new generation sources. FERC, the federal regulator that oversees interstate electricity transmission, has a deadline of April 30, 2026 to respond to the directive. The proposed rule would allow large load customers to request co-located generation and grid connections simultaneously, cutting study times and reducing the cost of required network upgrades. It would also require those customers to fund the full cost of the grid infrastructure they need, a provision aimed at ensuring other ratepayers are not left with the bill. (Gibson Dunn)
U.S. Utilities Announce $1.4 Trillion in Capital Spending Through 2030
A new analysis of 51 U.S. investor-owned utilities, released this week, found they plan to spend a combined $1.4 trillion on infrastructure through 2030, a 27% jump from last year’s $1.1 trillion projection and roughly double the $700 billion invested across the entire previous decade. Duke Energy has committed $102.2 billion and Southern Company pledged $81.2 billion. The spending covers new power plants, transmission line upgrades, distribution modernization, and grid hardening. The surge reflects utilities trying to keep pace with data center load requests that are arriving faster than steel can be put in the ground. For energy investors, this is the clearest signal yet of where capital is flowing at scale. (Tech Insider)
Have fun this week
Will
Sources
Oracle Agrees to Buy Power From Bloom for AI Data Centers | Bloomberg
Bloom Energy and Oracle Expand Strategic Partnership to Deploy up to 2.8 GW | Bloom Energy
Oracle jumps for a second day, Bloom Energy soars 22% on AI data center power deal | CNBC
Texas Sees Power Demand Quadrupling by 2032 on Data Center Boom | Insurance Journal
Texas lawmakers held a hearing on data centers. Here are 4 key takeaways | KUT Radio
US Power Use to Beat Record Highs in 2026 and 2027 as AI Use Surges, EIA Says | EnergyNow
Judge Orders GE to Stay in Vineyard Wind Contract | Vineyard Gazette
5 offshore wind farms move ahead after Trump admin misses appeal deadline | Electrek
Trump-branded AI data center megaproject stalls, CEO departs | Axios
AI Nuclear Power Developer Fermi Slides On CEO’s Abrupt Exit | Bloomberg
Gas-Turbine Prices Surge, Crimping Efforts to Power Data Centers | Bloomberg
U.S. Power Boom Triggers Global Gas Turbine Shortage | OilPrice.com
US Utilities Plan $1.4T for AI Data Centers: 27% Capex Surge | Tec


